|
RESTORATION APPEAL FUND
(A Committee of the Parochial Church Council)

Download a copy of our Restoration
Appeal brochure here.
Our Mission
- Maintaining the fabric of the building
for regular worship.
- Providing facilities and an ambiance to
enable people of all ages, health and mobility to participate
in services and events.
- Stewardship of the building for the benefit
of future generations.
|
| |
|
Our Patrons
|

|
 |

|
|
His Grace The
Duke of Northumberland
|
The Right Reverend
Martin Wharton,
Bishop of Newcastle |
The Right Honourable
Alan Beith MP
|
|
|
 |
|
|
|
| |
Mrs Fiona Hall, MEP
|
|
Timothy Kirkhope
Esq, MEP
|
|
| |
Progress So Far
Since the launch of the Restoration Appeal Fund
in 2000 a tremendous range of work has been completed, thanks in full
measure to the hard work and generosity of Parishioners, Visitors, Local
Enterprise and Business.
| |
|
Phase 1 was completed
in early 2004:
- A new Heating System.
- A new Sound System & Hearing Loop.
- New Outer Doors.
- Disabled Ramp & Handrails.
- Repositioning of the Altar & Altar
Rails.
|
|
| |
 |
Project 1 was completed
in December 2005:
- Repair and renew the floor at the Crossing
- Realign the pulpit to improve sightlines
between the altar and congregation.
- Installed lighting over the East - West
public footpath through the Churchyard.
- Improve Fire Escape, Bridge & Footpath
from Priest's Door in Chancel.
- Repair Rose Window.
This work has made
St. Lawrence Church a much more welcoming, inclusive and comfortable
place in which to worship and work.
|
| |
|
Project 2 was completed
in 2006:
- Re-point the stonework of the Spire and
Belfry (upper part of the Tower).
- Replace some broken stones.
- Renew the lightening conductor
- Free up and grease the kingpin of the weathervane.
- Repaint the metal tie plates and clock
brackets on the Tower.
- Install lead lined steel hoppers
in the ‘lucarnes’ (openings) of Spire to catch and
dispose of the water dripping from the worn head stones.
This work was paid for by funds raised again
entirely from local sources.
|
 |
|
|
|
|
The Future
Following receipt of the Quinquennial Report
in 2004, the Restoration Appeal Fund Committee and Parochial Church
Council reviewed the work to be carried out in the immediate and
longer-term future and divided it into three Projects. The first
two projects are complete – see ‘Progress so Far’.
Project 3
Shortly after the tower was added in the 13th
Century, two buttresses were built at the west end of the north
wall, presumably to prevent lateral movement. The Church is built
on alluvial sand & clay with hard sandstone bedrock some 20
metres down. Medieval foundations were very shallow – the
north wall is built upon a line of boulders about a metre down.
The Victorian roof beams are longer in the centre of the nave than
at the east and west ends.
The north wall continues to rotate outwards
and further movement must be arrested to prevent an irrecoverable
situation being reached.
This massive Project will take several years
to complete and will require a fundraising effort far beyond our
immediate hinterland of well wishers. We have raised substantial
funds to complete the work to date, but hereafter will need to appeal
to National and International sources of Grant Aid. Since some of
this will be on a matched funding basis, it remains crucial to our
success that local initiatives and efforts are maintained and increased
to allow work to continue unhindered into the future.
|
| |
 |
Investigative Work on the North
Wall has been completed.
- Core drilling into wall.
- Trial pits at base of wall.
- Boreholes in Churchyard.
- High level inspection of north wall and
top of arcade of pillars.
Result of the investigation:
- The wall is in a parlous condition.
- Rotational movement is continuous and potentially
progressive.
- Centre is 490mm out of true since it was
built in the 12th century.
- Movement since 1968 is 49mm.
- Urgent action necessary.
|
| |
|
St. Lawrence Church has been placed on the
English Heritage 2007 ‘Buildings at Risk’ Register.
Stage 1 Project Development is planned for 2008. This includes a
Rectified Photography Survey and very detailed measurement of the
wall and arcade.
Construction Works.
The Stage 2 work is planned for 2009. Reinforced
concrete beams will be inserted into the vertical pilasters, joining
up with a new horizontal beam inside the wall. Concrete pads in
churchyard supported by piles will be joined under ground with the
vertical beams. The detailed work required and hence the cost is
likely to change during Stage 1, but work MUST be started within
two years.
Funding - How Much?
The estimated cost of £516,000 is subject
to the results from Stage 1 Project Development. English Heritage
has awarded us a grant of £25,000 towards Stage 1 and an 'in
principle' £275,000 towards Stage 2.
This total of £300,000 is a massive indication of the importance
and urgency of this Project.
With what we have raised to date, together
with the eventual refund of VAT we are left with a shortfall of
£70,000.
We are applying to other Grant Aid Bodies
and of course continuing our local and Parish efforts.
Please help us to raise this money in 2008
in time to save our wonderful Church.
|
How to Help
We need your support to help us to raise funds to
carry forward Project 3 of the Restoration Programme and enable us to
plan future work as the need arises to minimise deterioration of this
ancient building.
You can help by:
- Offering your prayers & practical support
to our appeal.
- Participating in Parish fundraising activities.
- Joining the ‘Friends of Warkworth Church’
scheme.
- Welcoming visitors to the Church and encouraging
them to support us.
- Making regular ‘gift aided’ donations.
Bank details available.
- Making a one-off ‘gift aided’ donation.
- Donating by cash or cheque – Pay PCC Warkworth.
- Remembering St. Lawrence Church in your will
– very tax efficient for one’s beneficiaries.
Andy Webber
Chairman, Restoration Appeal Committee
5 February 2008.
|